Satpura Thermal Power Station,Sarni :
LOCATION 18 K.M. FROM GHORA DONGRI RAILWAY - STATION DIST –BETUL
CAPACITY 1330 M.W.
SOURCE OF WATER TAWA DAM; LAKE AREA 2893 ACRE
FUEL PRIMARY FUEL -COAL
SECONDARY FUEL –FURNACE OIL/HSD
COAL SOURCE WESTERN COAL FIELD LIMITED
COAL AREA PATHAKHEDA, KANHAN, PENCH, NAGPUR, CHANDRAPUR, WANI
MODE OF TRANSPORT RAIL /ROAD/BELT
COAL LINKAGE 79.2 LMT (appx.) PER ANNUM (2007-08)
POWER EVACUATION 400 K.V. LINES STP – ITARSI/ INDORE
STP – KORADI/ BHILAI
220 K.V. LINES STP – ITARSI (4)
STP - KALMESHWAR (1)
UNITS CAPACITY MW COMMISSIONING DATES MAKE TG SET MAKE BOILER
Unit I 62.5 DECOMMISSIONING ON 07-01-2014 GE USA B&W
Unit II 62.5 DECOMMISSIONING ON 05-12-2013 GE USA B&W
Unit III 62.5 DECOMMISSIONING ON 01-10-2012 GE USA B&W
Unit IV 62.5 DECOMMISSIONING ON 05-12-2013 GE USA B&W
Unit V 62.5 DECOMMISSIONING ON 01-02-2013 GE USA B&W
Unit VI 200 01-07-1979 BHEL BHEL
Unit VII 210 20-09-1980 BHEL BHEL
Unit VIII 210 25-01-1983 BHEL BHEL
Unit IX 210 07-02-1984 BHEL BHEL
Unit X 250 18-08-2013 BHEL BHEL
Unit XI 250 16-03-2014 BHEL BHEL